This article is for general information only. It is based on publicly available reports and official materials as of 18 November 2026. The project remains subject to approvals and change. Please read the full disclaimer at the end.
The coast we cover, from Ventimiglia to Imperia, has waited a long time for the Aurelia Bis to be finished west of Sanremo. On 18 November 2026, Liguria’s president, Marco Bucci, said the Region had spoken with Sanremo’s mayor, Alessandro Mager, and that they were agreed on returning to ANAS’s original project, “so that we can go forward quickly.” He named two remaining problems: the continuation towards Ospedaletti, and the San Martino interchange. ANAS, he added, wants to do the work. No start date was given. He also said the via regionale had been authorised so that the Region’s own offices could carry it out, and that there was “the intention of everyone to begin work.” This is a separate scheme from the Aurelia Bis already under construction at Savona.

What is already open, and what is still on the drawing board
A bypass already links Taggia and Arma di Taggia with Sanremo. The first stretch, about seven kilometres from Valle Armea to San Martino, opened in 1994; later sections continued through the San Lazzaro/hospital junction and the San Giacomo tunnel to Sanremo Centro, opened in June 2011. Concessioni del Tirreno, the successor to Autostrada dei Fiori since June 2024, operates the Arma di Taggia–San Martino stretch; ANAS manages the state-road sections into the centre (SS 718).
The westward completion has never been built. In September 2023, ANAS presented a corridor of about 17 kilometres in three lots, as an alternative to the historic Aurelia (SS 1) and, when needed, to the A10:
- Lot 1 — the Sanremo variant: about 4.2–4.3 km from the San Giacomo tunnel to Cava Cangiotti (Pian di Poma / Bonmoschetto), mostly in tunnel.
- Lot 2 — Sanremo to Ospedaletti: about 4.4 km, mostly in tunnel, from a Pian di Poma / Via Padre Semeria junction to a west Ospedaletti roundabout.
- Lot 3 — Ospedaletti to Ventimiglia: about 8.65 km through Bordighera, Vallecrosia and Camporosso, ending at the SS 20.
The official purpose is to take medium- and long-distance traffic off the historic coast road, leave that road for local and tourist use, and offer an alternative if the A10 is closed or congested. It would be a C1 extra-urban road, with one 3.75-metre lane in each direction.

The “original” ANAS design, and the version that dropped the junctions
The dispute is about Lot 1. In January 2023 ANAS presented four options; on 13 February, after talks with the Comune, the Region, the Province and the government, Alternative E was chosen. It ran 4.225 kilometres, with at-grade roundabouts — at the Comune’s request — at Sanremo Centro, Sanremo Foce (towards Corso Inglesi), Via Padre Semeria and Cava Cangiotti. The cost was put at about €300 million, with works hoped for early 2025; they did not start.
The Consiglio Superiore dei Lavori Pubblici later asked for a revision, warning that too many urban roundabouts would mix town and long-distance traffic. After a ministry meeting on 23 July 2025, ANAS dropped the Foce junction and the Via Padre Semeria link. In March 2026 it gave a positive opinion, with prescriptions, on that lighter scheme: two grade-separated junctions only, at Sanremo Centro and at Pian di Poma (Cava Cangiotti, in two phases). About 3.2 kilometres would be in tunnel, and the cost fell to about €328 million, from around €415 million.
In August 2026 Sanremo’s council asked for those intermediate junctions to be restored. On 5 November La Stampa reported that ANAS had two projects ready — one with the junctions and one without — and that the town would have to choose before the conferenza dei servizi. Bucci’s 18 November remarks sit in that context, but he did not publish a new drawing.

Costs, funding and the San Martino ramp
The September 2023 ANAS presentation put a parametric €1.2 billion on the whole corridor (€300 million, €280 million and €620 million for the three lots). Those figures have not been funded. CIPESS approved the ANAS–ministry 2021–2025 programme contract on 21 March 2024, but ANAS’s August 2026 report said only €8 million was actually available, and only for design. Without a construction grant, there is no approved start for Lot 1, let alone the later lots.
The San Martino interchange is a separate, more advanced project, and is not in the ANAS feasibility design. Concessioni del Tirreno is promoting it, under a 2022 convention, as a new exit ramp onto Via della Repubblica, to ease traffic on Corso Cavallotti and in San Martino. A favourable conferenza dei servizi opinion was reported in September 2026; assessor Massimo Donzella had spoken of a 240-day programme once works began. Local reporting in early November said a 2027 start was expected — a reported expectation, not an official start notice.

Timeline
- 1994 and June 2011. The existing bypass opens in stages, from Valle Armea to Sanremo Centro.
- 9 May 2022. A special commissioner is appointed for Lot 1.
- 2023. Alternative E is chosen in February, with works hoped for early 2025. In September the 17 km, three-lot corridor is presented at a parametric €1.2 billion.
- 21 March 2024. CIPESS approves the programme contract; later official reporting puts available funding at €8 million, for design only.
- March 2026. Positive opinion, with prescriptions, on the lighter Lot 1 (about €328 million; 1,500 days). Local reporting said first cars could, if all went well, use it by the end of 2030.
- May–November 2026. Favourable opinion reported on the San Martino ramp. Sanremo asks for the intermediate junctions back; ANAS is reported to have both designs ready. Bucci’s 17–18 November remarks, summarised above, still give no start date.
No official start or completion date has been published for these lots. The early-2025 start has already been missed. The end-2030 figure assumed the lighter design and funding that has not been granted.
What this could mean for buyers
If Lot 1 is approved, funded and built, through-traffic would be taken off the historic Aurelia and off streets in central and western Sanremo — above all around Corso Inglesi and the Foce, Via Padre Semeria, Bonmoschetto, Pian di Poma and Cava Cangiotti. Later lots would extend that relief towards Ospedaletti, Bordighera, Vallecrosia, Camporosso and Ventimiglia.
That is not a reason to assume a rise in property values. We are not attaching any percentage, euro figure or “uplift” to homes here, and nobody should buy on the assumption of one. Values depend on the wider market, the condition of individual buildings, and how long and how disruptive any works — including possible expropriations — prove to be.
No official figures have been published for journey-time savings to Nice airport or Genoa; the A10 remains the main route to both. In mid-November 2026 Bucci said maintenance on the motorway towards Ventimiglia could still last a year and a half to two years. If the reported 2027 start holds, the nearer change is the San Martino exit ramp; the larger westward bypass still depends on a settled design, remaining approvals, and construction funding.
A separate waterfront scheme, the Porto Vecchio regeneration, is also before the Comune this week. Anyone considering a purchase along this coast, from Ventimiglia to Imperia, is welcome to talk it through with us.
Sources
Facts in this article are taken from official papers and reports consulted on 18 November 2026. Where later figures revise earlier ones, notably the cost and junction layout of Lot 1, the later figure is used and the change is noted in the text.
- Regione Liguria press releases, 18 January, 13 February and 4 September 2023, including the official Alternative E drawing “tracciato variante Sanremo Aurelia-bis”
- ANAS presentation, 4 September 2023, “S.S. n.1 Aurelia — Adeguamento e messa in sicurezza del tratto Sanremo–Ventimiglia” (GE270)
- Ministry of Infrastructure and Transport, 23 July 2025, “Aurelia Bis, confronto positivo al Mit tra Comune di Sanremo e Anas”
- CIPESS delibera no. 6/2024 of 21 March 2024, approving the ANAS–ministry programme contract 2021–2025
- ANAS report signed by commissioner Claudio Andrea Gemme, protocolled at the Comune di Sanremo on 20 August 2026, as reported locally
- La Stampa, 5 March 2026 and 5 November 2026; Riviera Time, 16 June 2017 (on the 1994 opening)
- Other contemporary local and national press reporting consulted on 18 November 2026
Explore Properties Along the Western Ligurian Coast

Plan Your Complete Italian Property Acquisition & Ownership Budget
Calculate Italian registration tax (Prezzo-Valore vs. Prima Casa), notary and geometra allowances, concierge support, and 2026 municipal IMU across Ventimiglia, Bordighera, Ospedaletti, Sanremo, Taggia, Santo Stefano, San Lorenzo, and Imperia.
Planning a Move or Purchase on the Italian Riviera?
Speak directly with Raffaello Sappa about finding a villa or apartment between Ventimiglia, Bordighera, Sanremo and Imperia, or managing a home you already own.
- Personal reply within 24 hours
- Fluent English & Italian
- No obligation, whether ready now or planning ahead