Sanremo’s Porto Vecchio regeneration: what the waterfront plan means for buyers

May 2026 design: two perspective views of the proposed waterfront and a plan of the relocated pavilions.
A buyer’s guide to Sanremo’s €110 million Porto Vecchio plan: the latest designs, a sourced timetable, the streets most affected, and what four years of works could mean.

This article is for general information only. It is based on publicly available reports and promoter materials as of 18 November 2026. The project remains subject to approvals and change. Please read the full disclaimer at the end.

Sanremo’s old harbour sits at the heart of the Western Ligurian coast we cover, from Ventimiglia to Imperia. On 18 November 2026, Porto di Sanremo Srl — the company controlled by the Reuben Brothers group, which already owns Portosole — was due to present an updated scheme for the Porto Vecchio to Mayor Alessandro Mager and municipal officers at Palazzo Bellevue. Local reporting puts the latest cost estimate at about €110 million, with works lasting four years if and when they begin.

The meeting is intended to clear the way for the decisive conferenza dei servizi, the formal sign-off that still has to take place. The economic-financial plan also has to be updated. Nothing here is a finished consent, but the published drawings and timetable are now clear enough for buyers to see what could change, and when.

May 2026 design: two perspective views of the proposed waterfront and a plan of the relocated pavilions.
May 2026 design: two perspective views of the proposed waterfront, with a plan of the relocated pavilions and sea-facing square. Render: Reuben Brothers / AMDL CIRCLE. Illustrative only.

What the latest published plan includes

The scheme is a project-financing concession, awarded in April 2024. Porto di Sanremo Srl would design, build and then manage the harbour.

A tunnel under Via Nino Bixio, now described as about four metres high, is the public-interest heart of the plan. Compatible Riviera Trasporti buses could use it; heavier goods vehicles, and on current reporting coaches, would still travel along Via Roma. September 2026 coverage placed the western entrance just before the Istituto Mater, with a straight exit onto Via Nino Bixio before the San Francesco bridge. A five-metre tunnel was dropped because the ramps would have been too steep.

A 200-space underground car park would sit beneath the area of the waterfront bars, or baretti, with access through the Croce Rossa underpass near the post office. It is now separate from the tunnel. Earlier versions spoke of 135 spaces, then around 120; the 200-space layout is the one described in early November 2026.

The bars would be demolished and rebuilt, so that they do not form a solid wall between the town and the water. In front of the new premises the plan shows a sea-facing square in a larger pedestrian area. Existing concession-holders are, according to local reporting, to be offered guarantees on trading space and compensation during the works.

Typical pavilion for the rebuilt waterfront bars, from the May 2026 design.
Typical pavilion for the rebuilt waterfront bars, from the May 2026 design. Render: Reuben Brothers / AMDL CIRCLE. Illustrative only.

Piazzale Vesco, in front of the harbour master’s office, is to remain public, and available for events including the Sanremo Festival. The berths would be reorganised: larger yachts along a strengthened main pier; the sports clubs, including Yacht Club Sanremo and Canottieri Sanremo, next to the bars; and professional and small-scale fishing at the root of the long pier, towards Forte di Santa Tecla, with a new small-scale fish market there. These arrangements may still change.

March 2023 definitive masterplan compared with the April 2026 variant.
March 2023 definitive masterplan above, and the April 2026 variant below, which frees Piazzale Vesco and moves fishing towards the root of the southern pier. Later months brought further changes, including the four-metre tunnel and the 200-space car park. Render: Reuben Brothers / AMDL CIRCLE. Illustrative only.

Timeline

Dates below can be tied to published reports or official acts. Later steps are still only hopes or working assumptions.

  • 2017. Porto di Sanremo Srl, then associated with Walter Lagorio, put forward the first proposal, prepared by the Sanremo studio Marco Ceschia Viganò (also reported as Calvi–Ceschia–Viganò). The Comune declared it of public interest.
  • November 2022. The Reuben Brothers group, already owner of Portosole, acquired the company in full.
  • 27 April 2024. The Comune awarded the concession to Porto di Sanremo Srl, the only bidder, by determina no. 1827 (annual fee €110,000, index-linked, over 65 years; tender lifetime value more than €600 million).
  • August 2025. A preliminary conferenza dei servizi closed with the authorities’ observations largely taken as received. Regione Liguria still required a ministerial view on whether a full environmental impact assessment would be needed, which can add a year.
  • 3 and 6 October 2025. Giunta delibera no. 199 set new design directions, including a five-metre tunnel and a public Piazzale Vesco, followed by a single-subject session of the Consiglio Comunale.
  • 27 April 2026. The company and its designers presented a variant at the Comune. Boards from that day carry the title block “AMDL CIRCLE × Porto di Sanremo Srl”.
  • May–September 2026. The Comune asked for a wider opening through the baretti and received further revisions. By September the tunnel was described as about four metres high, with the car park given its own Croce Rossa access. Mayor Mager set a 10 November deposit deadline and spoke of the end of 2027 as a hope for the start of works, not a fixed date.
  • 7–18 November 2026. Il Secolo XIX reported that the deposit had slipped to 18 November, and that the car park had been enlarged from 120 to 200 spaces. On 18 November the company was due to present the updated papers. Next come the decisive conferenza dei servizi, the updated economic-financial plan, and the remaining administrative steps — none of them yet dated.

On the most favourable published scenario, works could start in the second half of 2027 and last 48 months. That is the wording used in local reporting on 18 November. If that held, completion would fall around the second half of 2031 — the arithmetic of a late-2027 start plus 48 months, not an official completion year. The start itself still depends on approvals that have not been given.

The harbour today, beside a September 2026 plan of the tunnel and car park.
Left: the harbour and Via Nino Bixio as they are today. Right: a September 2026 plan of the tunnel and car park, with pink marking the ramps, blue the tunnel, orange the car park, and green a new link from Corso Trento e Trieste towards Via Bixio. Render: Reuben Brothers / AMDL CIRCLE. Illustrative only.

What this could mean for buyers

If the scheme is approved and built broadly as now described, the parts of Sanremo most closely tied to it are the port itself, Via Nino Bixio, the streets around the post office and the Croce Rossa underpass, the approaches from Corso Trento e Trieste, Piazzale Vesco, and the old town and Marina behind the waterfront. A more pedestrian, sea-facing harbour, with a public square that can still hold Festival events, is the sort of civic improvement that often supports interest in nearby streets — over time, and only if the work is finished.

That is not a forecast. We are not attaching any percentage, euro figure or “uplift” to property in Sanremo, and nobody should buy on the assumption of one. Values here depend on the wider market, the Festival and the town’s year-round economy, the condition of individual buildings, and how long and how disruptive the works prove to be. A long waterfront site can also make daily life less pleasant while it is under construction.

The first demanding job would be the tunnel under Via Nino Bixio, with effects on the cycle path, the Istituto Mater, the Croce Rossa underpass and the post office. The site is expected to be divided into lots, so the whole port is not closed at once, but four years is a long time in a town built around the Festival, Milano–Sanremo and the summer season. One report has suggested that works would ideally not start until the new car park in Piazza Eroi is finished. The tunnel will not take heavy goods vehicles off Via Roma; without a wider update to the town’s 2015 traffic plan, congestion could simply move onto Via Roma, Corso Mombello and Via Nino Bixio.

In the nearer term, the story is planning risk, noise, traffic and a waterfront that will be a building site. In the longer term, if approvals are granted and the work is finished, Sanremo would have a reorganised harbour and a much altered Via Nino Bixio. How far that supports values around the port will only be clear in practice. A related public-works story is the Aurelia Bis around Sanremo. Anyone considering a purchase in Sanremo, or comparing it with other towns on our stretch of coast from Ventimiglia to Imperia, is welcome to talk it through with us.

Sources

Facts in this article are taken from reports and official references consulted on 18 November 2026. Where later articles revise earlier figures, notably the size of the car park and the height of the tunnel, the later figure is used and the change is noted in the text.

  • Il Secolo XIX, 7 November 2026, “Il parcheggio sale a 200 posti”; and the September 2026 report of the meeting with Mayor Mager
  • Vivere Sanremo, 19 September 2026; La Stampa, 15 April and 18 November 2026; Prima la Riviera, 15 May 2026 and 3 October 2025; Riviera Time, 6 October 2025
  • Comune di Sanremo, determina no. 1827 of 27 April 2024 (transparency portal); Giunta delibera no. 199 of 3 October 2025, as reported by the Comune and the local press
  • Other contemporary local press reporting consulted on 18 November 2026
CURATED PORTFOLIO

Explore Properties Along the Western Ligurian Coast

Western Ligurian Coast — Coastal Buyer and Rental Planner
INTERACTIVE BUYER & RENTAL PLANNER

Plan Your Complete Italian Property Acquisition & Ownership Budget

Calculate Italian registration tax (Prezzo-Valore vs. Prima Casa), notary and geometra allowances, concierge support, and 2026 municipal IMU across Ventimiglia, Bordighera, Ospedaletti, Sanremo, Taggia, Santo Stefano, San Lorenzo, and Imperia.

Open the Buyer & Rental Planner →£ / € / $ display · Print or save your bespoke HTML/PDF plan
Private Property & Concierge Advisory

Planning a Move or Purchase on the Italian Riviera?

Speak directly with Raffaello Sappa about finding a villa or apartment between Ventimiglia, Bordighera, Sanremo and Imperia, or managing a home you already own.

Direct to Raffaello Sappa · Director, The Riviera Concierge Ltd (UK)